temporary driveway assistance devices reduce costs for street reconstruction: webster city

heavily-trafficked corridor receives much-needed improvements

initially constructed in 1930, u.s. highway 20 (now known as east second street), is a busy two-lane roadway that stretches through webster city. with the pavement extending to the east of lyons creek in need of replacement, webster city contracted snyder & associates to lead improvement efforts. our firm was also tasked with improving the roadway geometry and updating the clear zone area to meet current design standards. additionally, an 8′-wide sidewalk was needed along the corridor to increase pedestrian and bicyclist safety.

the key design and construction considerations were focused on right-of-way (row) access and the need to maintain traffic flow during the reconstruction process. to avoid any new acquisitions and streamline the environmental permitting process, the city requested that construction be confined to the existing row. further, four commercial businesses, a mobile home community, a 世界杯足球比赛预选赛 dog park, a cultural center, 15 residential driveways, and multiple industries just to the east of the project corridor that employs several hundred people required that the roadway remain open to traffic at all times.

iowa’s first use of temporary driveway assistance devices

snyder & associates reviewed several alternatives for temporary lanes to maintain two-way traffic. all were deemed too expensive or would require additional grading outside of the existing row. the use of temporary signals, pilot cars, and flaggers was also considered. however, these options would reduce the project into smaller segments, take longer to complete, and be more expensive.

driveway assistance device (dad) communicating to motorists when it is safe to enter a one-lane work zone from a driveway or side street.

syncing with portable traffic signals, the driveway assistance device (dad) communicates to motorists when it is safe to enter a one-lane work zone from a driveway or side street.

greg karssen, pe, with snyder & associates researched an innovative, temporary traffic signal solution. when placed at each driveway entrance within the corridor, these portable signals can be synchronized with mainline, temporary road signals to properly route driveway and side street traffic with the mainline traffic. when a driver exits a business or residence, the temporary driveway signal is activated and the proper direction of travel is selected. the green cycle of the temporary mainline signal is then activated to merge driveway traffic into mainline traffic. the temporary signals use radar detection to facilitate traffic flow and are programmed to adjust the timing of the green cycle based on traffic volume.

the use of these temporary signals allows one-lane, two-way traffic through the work zone and prevents the need to construct a temporary pavement platform or use pilot cars or flaggers. an added benefit of this method is the distance between mainline signals is increased. this lengthens the work segments which allows work to be completed more efficiently with fewer stages.

the iowa dot had long been interested in using temporary signals to manage traffic access from residential and business driveways. the east second street project was the first in the state of iowa suited for the implementation of individual, temporary traffic signals to direct the flow of traffic for property owners.

clean water & sanitary sewer issues resolved

snyder & associates also investigated issues concerning the existing water main within the project corridor. this main had experienced 16 breaks in a 13 year period. it was discovered that corrosive soils within the project corridor were contributing to the water main breaks. the replacement and relocation of the water main to an area outside of the new paving and storm sewer area were included with the project.

also, the sanitary sewer along the corridor was found to have a several hundred foot-long stretch with inadequate slope. sewage flow was slowed in this section, allowing the water to cool. this caused fats from two meat processing plants located upstream to coagulate and clog the line. as a result, thousands of dollars per year were spent to remove clogs. to improve flow and reduce maintenance costs, the sanitary sewer was replaced and the slope was increased.

client

webster city

client type

project type

wade greiman, p.e.

wade greiman, p.e.

transportation business unit leader

related projects

aerial rendering of the grand avenue roadway extension in west des moines|map of national flood hazard layer of the project area|image of construction taking place for grand avenue extension in west des moines iowa with construction workers and cement trucks in the background|newly poured roadway with road crew working in the background.|image of construction taking place for grand avenue extension in west des moines iowa|new bridge over johnson creek with earthwork still to complete underneath.|view of the johnson creek bridge along grand avenue with the new monuments installed on either side.|custom-designed monuments for the city of west des moines

grand avenue extension in west des moines opens additional area for development

to provide access to microsoft's new data center and open additional area for development in southwest west des moines, city leaders contracted with snyder and...
a man running on trail underneath bridge|creek bank underneath bridge|map of the new clear creek trail alignment around the interstate 80/380 interchange|workers install one of the bridges over clear creek|decorative concrete castings for clear creek trail connection|clear creek trail connection bridge|trail underneath bridge in coralville iowa

clear creek trail connection fills critical multi-modal gap: coralville, iowa

the clear creek trail project has emerged as a significant addition to the ongoing efforts to enhance connectivity and recreational opportunities in johnson county....
exposed siphon at omaha papio creek|drone map of the papio creek in omaha ne|papio creek stream

safeguarding critical infrastructure and water resources: omaha’s “papio” creek

in march 2019, the city of omaha faced a significant threat to its critical infrastructure under west papillion creek (known to locals as papio creek). a disastrous...
||restoration from marsh to top tier course with featuring bright green golf course and trees in background|

tpc wisconsin emerges as a premier golf course

in the heart of madison, wisconsin, a remarkable transformation has occurred, reshaping the golfing experience for enthusiasts and professionals alike. dennis tiziani,...
ne 51st avenue intersection along us 69 reconstruction project.|intersection with traffic lights|intersection at ne 70th avenue intersection along the us 69 reconstruction project.|intersection of ne 60th avenue near the polk county sheriff's office along us 69 reconstruction.|median under construction|lidar image of us 69 reconstruction|snyder & associates transportation experts

us 69 reconstruction: paving the way for future growth in ankeny

in the heart of unincorporated polk county, a bustling two-lane corridor known as us highway 69 (ne 14th street) has long been a critical lifeline connecting des moines...
newly constructed roadway intersection|road traffic transitions into roundabout|improved traffic flow due to new corridor|snyder & associates worker surveying roadway construction|group of people attending a ribbon cutting for new roadway|tower terrace roadway map

tower terrace road upgrades fill gap in northern connector initiative

nearly two decades ago, planners for linn county and several surrounding communities — including cedar rapids, hiawatha, and marion — began laying the groundwork for an...
|||aerial rendering of hickman and interstate 35/80 diverging diamond interchange.||street level rendering of hickman and interstate 35/80 diverging diamond interchange.|||rendering of pedestrian tunnel underneath interstate 35/80 at hickman road diverging diamond interchange.|bridge abutments design treatment underneath interstate 35/80 diverging diamond interchange bridge.|||median treatment rendering underneath interstate 35/80 diverging diamond interchange bridge.|two pedestrian bridges over the interstate onramps

progress on the interstate 35/80 & u.s. 6 diverging diamond interchange upgrade

the exponential growth of communities, particularly in the western suburbs of des moines, has been nothing short of remarkable. the population of waukee, for example,...
||||

cedar heights drive reconstruction continues cedar falls corridor upgrades

for several years, the cedar falls community has been expanding its transportation network along the southern edge of town, including the greenhill road corridor. this...
south dakotas capitol building behind dredging equipment on lake|excavator on floating platform|excavator dredging from shoreline|sediment being pulled from lake bed|aerial view of capitol lake in south dakota|dump truck being filled with sediment from of south dakota's capitol lake

sediment buildup necessitates lake dredging project at south dakota capitol complex

one of the prominent features complementing the architectural beauty of the capitol complex in pierre, south dakota, is the 9.5-acre capitol lake. fed by a naturally...
people enjoying 世界杯足球比赛预选赛
 launch at hubbard park|rendering of a canoe launch in wisconsin||||kinds in the water at hubbard park launch|families playing in the river at hubbard park launch

water access upgrade expands amenities at hubbard park: shorewood, wisconsin

hubbard park in the village of shorewood is a local landmark in this wisconsin community. located on a nearly five-acre, 1,400-foot-long strip of land between the...

more than 45 years

serving clients around the country

db+