obsolete bridge design leads to new construction over the west nishnabotna river along interstate 80

major interstate bridges require updated design profiles

extending 306 miles across the state, interstate 80 is iowa’s longest interstate highway. it’s also one of iowa’s busiest roadways, carrying the vast majority of the truck traffic through and around the state. this heavy traffic also results in the premature aging of highway infrastructure, particularly bridges and roadway surfaces. in a coordinated effort to replace two interstate 80 bridges over the west nishnabotna river, the iowa dot partnered with snyder & associates and their affiliate 2022足球世界杯小组赛赛程 to design and oversee construction on this project.

each of the original 300′-long x 30′-wide continuous welded girder bridges carry two lanes of interstate traffic — one bridge for westbound and one for eastbound traffic. not only were these bridges structurally deficient, their narrow design also meant they were functionally obsolete. current design guidelines for new interstate bridges require the design have full-width shoulders in addition to the two 12′-wide travel lanes. the replacement design called for two 319′-long x 40′-wide continuous welded girder bridges to meet the required guidelines.

additionally, the current roadway approaches leading to the bridges did not have the necessary “clear zone” geometry required by the current federal highway administration (fhwa) minimum standards. a clear zone is an unobstructed area adjacent to a roadway that allows a driver to stop safely, or regain control of a vehicle that has left the roadway. the necessary addition of this feature provides an enhanced level of safety to all motorists.

multiple services provided for interstate bridge project

the 2022足球世界杯小组赛赛程 and snyder & associates design team provided numerous services over the course of this project, including:

time & design challenges to meet budgetary constraints

from the outset of the project, the design team was presented with numerous challenges. the first was the need for an accelerated design to meet the funding distribution requirements. because of this, the team was faced with a short window to complete the design. the second challenge was the need to maintain traffic flow along the interstate during the entire construction period. finally, the state desired a low-maintenance bridge to keep future costs down.

the professionals at 2022足球世界杯小组赛赛程 and snyder & associates coordinated with multiple offices of the iowa dot to prepare preliminary plans with hydraulic analysis and documentation, and final bridge and roadway design plans that met the shortened timeframe. to maintain full interstate functionality during the project, one bridge at a time was removed and replaced. this allowed for the use of traffic crossovers to shift traffic away from the bridge under construction. portable message boards placed several miles in advance of the construction zone alerted drivers to the approaching crossover and bridge construction.

interstate bridge construction & maintenance considerations

to keep future maintenance expenses in-check, the replacement bridges feature weathering steel girders, also known as beams. weathering steel girders develop a protective rust barrier that doesn’t require periodic painting. the girders were also designed to specific depth constraints to achieve the required freeboard clearance above the river’s design flood, minimize transverse stiffeners, and minimize steel fabrication costs. freeboard is the clearance between the bottom of the bridge girders and the high water surface elevation. an appropriate amount of freeboard allows for the safe passage of ice and debris under the bridge.

our team designed the bridge so that no joints were necessary for the bridge deck. the entire bridge is tied together as one unit, where some bridges are designed in such a manner that allows for independent movement between the top portions of the bridge (known as superstructure) and the bottom segments (known as substructure). the absence of deck joints extends the life of the pavement by preventing salt-laden runoff from leaking down to the supporting structural elements below. salt and moisture accelerate deterioration and can require costly maintenance or create the potential for expensive repairs.

the plan also called for t-piers supported on subsurface foundations that increase durability over their service life. finally, to maximize economy and ensure quick construction, standard materials and construction details were used where appropriate in the bridge designs to further decrease expenses.

this interstate bridge replacement project is a prime example of how the 2022足球世界杯小组赛赛程 and snyder & associates team works in conjunction with state agencies to create comprehensive roadway and bridge designs quickly and efficiently.

client

iowa dot

client type

project type

no team members assigned to this project.

related projects

aerial rendering of the grand avenue roadway extension in west des moines|map of national flood hazard layer of the project area|image of construction taking place for grand avenue extension in west des moines iowa with construction workers and cement trucks in the background|newly poured roadway with road crew working in the background.|image of construction taking place for grand avenue extension in west des moines iowa|new bridge over johnson creek with earthwork still to complete underneath.|view of the johnson creek bridge along grand avenue with the new monuments installed on either side.|custom-designed monuments for the city of west des moines

grand avenue extension in west des moines opens additional area for development

to provide access to microsoft's new data center and open additional area for development in southwest west des moines, city leaders contracted with snyder and...
a man running on trail underneath bridge|creek bank underneath bridge|map of the new clear creek trail alignment around the interstate 80/380 interchange|workers install one of the bridges over clear creek|decorative concrete castings for clear creek trail connection|clear creek trail connection bridge|trail underneath bridge in coralville iowa

clear creek trail connection fills critical multi-modal gap: coralville, iowa

the clear creek trail project has emerged as a significant addition to the ongoing efforts to enhance connectivity and recreational opportunities in johnson county....
overlaid pavement on 1st ave with railroad crossing in the background|aerial view of ellis boulevard and 6th street nw connector & 1st ave rehabilitation in cedar rapids iowa|aerial view of ellis boulevard and 6th street nw connector & 1st ave rehabilitation in cedar rapids iowa|aerial view of ellis boulevard and 6th street nw connector & 1st ave rehabilitation in cedar rapids iowa|railroad crossing|roundabouts streamline traffic flow|cars driving around the roundabout creating efficient traffic flow|1st ave & 6th street intersection facing north before & after construction

ellis boulevard & 6th street nw connector & 1st avenue rehabilitation: cedar rapids

a 2022世界杯32强预选赛 initiative performed in the community of cedar rapids identified a critical need for better connections and smoother traffic flow between the kingston...
roundabout in anamosa iowa|roundabout in anamosa iowa|overview of us 151 grade separation and roundabout in anamosa iowa|roundabout design showcasing lighting and signage in anamosa iowa|man cutting the ribbon for us 151 grade separation and roundabout in anamosa iowa||us 151 grade separation and roundabout: anamosa

us 151 grade separation and roundabout: anamosa, iowa

in a strategic move to address safety concerns and bolster regional connectivity, the city of anamosa required a unique transportation solution to address a regional...
ne 51st avenue intersection along us 69 reconstruction project.|intersection with traffic lights|intersection at ne 70th avenue intersection along the us 69 reconstruction project.|intersection of ne 60th avenue near the polk county sheriff's office along us 69 reconstruction.|median under construction|lidar image of us 69 reconstruction|snyder & associates transportation experts

us 69 reconstruction: paving the way for future growth in ankeny

in the heart of unincorporated polk county, a bustling two-lane corridor known as us highway 69 (ne 14th street) has long been a critical lifeline connecting des moines...
newly constructed roadway intersection|road traffic transitions into roundabout|improved traffic flow due to new corridor|snyder & associates worker surveying roadway construction|group of people attending a ribbon cutting for new roadway|tower terrace roadway map

tower terrace road upgrades fill gap in northern connector initiative

nearly two decades ago, planners for linn county and several surrounding communities — including cedar rapids, hiawatha, and marion — began laying the groundwork for an...
|||aerial rendering of hickman and interstate 35/80 diverging diamond interchange.||street level rendering of hickman and interstate 35/80 diverging diamond interchange.|||rendering of pedestrian tunnel underneath interstate 35/80 at hickman road diverging diamond interchange.|bridge abutments design treatment underneath interstate 35/80 diverging diamond interchange bridge.|||median treatment rendering underneath interstate 35/80 diverging diamond interchange bridge.|two pedestrian bridges over the interstate onramps

progress on the interstate 35/80 & u.s. 6 diverging diamond interchange upgrade

the exponential growth of communities, particularly in the western suburbs of des moines, has been nothing short of remarkable. the population of waukee, for example,...
||||

cedar heights drive reconstruction continues cedar falls corridor upgrades

for several years, the cedar falls community has been expanding its transportation network along the southern edge of town, including the greenhill road corridor. this...
newly poured concrete roadway|construction workers pouring concrete for stormwater drainage|cement truck pours wet concrete onto newly established roadway|construction workers in large hole for sanitary sewer|crews lay wet cement

major street reconstruction project benefits waverly community

the 4th street sw corridor is a busy north/south thoroughfare in the heart of the waverly community. this busy stretch provides access to the bustling business district...
|||||led bridge lighting|couple walks across a lit up trail bridge at night||night time bridge lighting

trestle-to-trestle bridge over beaver creek reconnects urban loop

the 3.75-mile-long trestle-to-trestle trail connects the inter-urban trail in des moines to the johnston trail system on the north side of interstate 35/80. in the...

more than 45 years

serving clients around the country

db+