east manawa drive trail

confined construction due to nearby drainage canal

the east manawa drive trail involved situating a recreational trail within a narrow corridor of right-of-way with a minimal constructible area. the corridor was located between manawa drive and the existing lateral 5 concrete drainage canal serving southeast council bluffs and u.s. highway 92, which is also known as veterans memorial highway.

grass berm between roadway and trail

construction of the east manawa trail took place in a narrow corridor to accommodate a drainage canal nearby.

obtaining an accurate topographical survey was critical to the project. the survey required for design purposes needed to clarify areas of concern that resulted in a reduction of trail width from 10 feet to segments of eight feet while maintaining drainage over the top of the roadway curb and meeting required trail shouldering specifications. the narrow right-of-way contained multiple underground fiber-optic and telephone facilities, overhead power poles, a water main, hydrants, traffic signage, and two storm sewer outfalls all located between the edge of highway shoulder pavement and the east manawa drive curb. survey accurately located all above ground and underground utilities including depths which allowed the design to negate any additional construction costs to the city due to conflicts with the required storm sewer outfall modifications. situating of the trail on the foreslope required weaving the trail between several obstacles while maintaining required clearances and maximum trail centerline profile grades that didn’t adversely affect the highway foreslope. to achieve the finished product, the accuracy of construction staking was paramount.

property surveys were also required to delineate ownership between city and idot right-of-way and private properties. these surveys also correctly determined locations for planting approximately 100 trees along the east manawa corridor as part of the landscaping plan.

snyder & associates completed all aspects of the project including coordination with the iowa department of transportation for permitting, topographic and boundary surveys, construction documents, construction staking, construction observation, and construction administration.

client

city of council bluffs

client type

project type

rich voelker, p.e.

rich voelker, p.e.

transportation business unit leader

related projects

a man running on trail underneath bridge|creek bank underneath bridge|map of the new clear creek trail alignment around the interstate 80/380 interchange|workers install one of the bridges over clear creek|decorative concrete castings for clear creek trail connection|clear creek trail connection bridge|trail underneath bridge in coralville iowa

clear creek trail connection fills critical multi-modal gap: coralville, iowa

the clear creek trail project has emerged as a significant addition to the ongoing efforts to enhance connectivity and recreational opportunities in johnson county....
|||aerial rendering of hickman and interstate 35/80 diverging diamond interchange.||street level rendering of hickman and interstate 35/80 diverging diamond interchange.|||rendering of pedestrian tunnel underneath interstate 35/80 at hickman road diverging diamond interchange.|bridge abutments design treatment underneath interstate 35/80 diverging diamond interchange bridge.|||median treatment rendering underneath interstate 35/80 diverging diamond interchange bridge.|two pedestrian bridges over the interstate onramps

progress on the interstate 35/80 & u.s. 6 diverging diamond interchange upgrade

the exponential growth of communities, particularly in the western suburbs of des moines, has been nothing short of remarkable. the population of waukee, for example,...
||||

cedar heights drive reconstruction continues cedar falls corridor upgrades

for several years, the cedar falls community has been expanding its transportation network along the southern edge of town, including the greenhill road corridor. this...
||||||indian creek trail connection ribbon cutting

indian creek trail connection unites key marion neighborhoods

having doubled in population over the past three decades, the cedar rapid’s suburb of marion has been the dual beneficiary of a rapidly expanding metro area and the...
fixed up railroad bridge into a trail bridge|summer time light hits the trail bridge and water below|engineering interns learning how to pave the roads|shaded trail bridge|brand new trail bridge with beautiful greenery|black gated fence around a trail route|construction happening on a old railroad bridge

river’s edge trail connects iowa’s heartland

while it's been many years in the making and still has many miles remaining to construct, the river's edge trail is ideally positioned to take advantage of the scenic...
bike trail winding through the green forest|trail with black fencing one either side|freshly paved trail goes uphill towards a tree line|incomplete trail bridge|map of the rolling prairie trail system|paving underway in the middle of a storm|trail water drainage

rolling prairie trail provides rural link across iowa’s scenic landscape

when rail transportation in iowa peaked in the early 1900s, the state was home to more than 10,500 miles of track. as automobiles became the preferred mode of...
|prairie city welcome signage town square|large green plants and trees on either side of a bike trail|winding trail heads towards a casey's gas station|child bikes a trail through a small town in iowa|small town welcome sign with a trail and road next to it|prairie city town square||

red rock prairie trail provides scenic recreational opportunities

most trail 2022世界杯32强预选赛 in central iowa over the past two decades has centered around making connections. whether connecting small communities or social venues, providing...
bridge on the railroad highway trail|pre-construction of the railroad highway trail|bridge on the railroad highway trail|trail pavement of the railroad highway trail|map of the railroad highway trail

railroad highway trail connects western iowa communities

now standing at more than 50% complete, the dream of a completely off-roadway, multi-use trail network spanning the entire country keeps taking steps to becoming...
high trestle trail pedestrian bridge at night|oralabor road trail bridge|many citizens gathered for a bike ride|oralabor road trail bridge under construction|the snyder and associates transportation team for oralabor road trail bridge|many bicyclists riding along the high trestle trail bridge|family smiling as they ride across a trail bridge on bikes||||rich voelker

pedestrian tunnel & bridge showcase trail extension in ankeny — high trestle trail

shortly after the high trestle trail bridge over the des moines river was completed in 2011, the focus quickly shifted to continuing the trail south through the ankeny...
thick metal signage with large text|bicyclist ride past the council bluffs fire station|before construction on first ave|bicyclist happily wave at on down the bike trail|first ave trail in council bluffs|asphalt trail along high school athletic facilities|council bluffs bike trail

first avenue trail creates council bluffs connection

formally adopted by the city of council bluffs in 2015, the west broadway corridor plan was developed to guide the transformation of this busy stretch of roadways into...

more than 45 years

serving clients around the country

db+